When your
company is embarking on a new project, one of the
first decisions is who to appoint to run the program
or project. The quickest answer is to assign
a current manager to the task, usually the one with
the bulk of the activities for the project.
Yet, historically, those initiatives that everyone
felt were successful always had one key ingredient:
a strong, skilled leader. If the project duration
is long, will result in a major change to the company,
or originated outside of your organization, you
should consider appointing a dedicated project manager
that can provide structure and expertise.
In some
instances, the decision may not be clear cut. If not,
you should ask yourself the following questions:
What
is the bottom line for all stakeholder expectations?
It is critical
to learn why the business wants the project completed,
especially if you were not directly involved when
the project was formulated and approved, as was my
experience with the particular project that I will
use as an example. Speak
directly with all of the stakeholders, specifically
the business sponsors, before deciding whether to
bring on a project manager. Your own team
will have their perspective, but it may not include
the key reasons.
In my case,
meeting with the other stakeholders was invaluable.
They were able to clearly
explain to me that the current situation was contributing
to negative customer service that would continue daily
until the completion of the project.
They were also clear about what they needed, expected
and believed the IT department (and my operations
manager) had already committed to deliver. The
stakeholders wanted the application fixed before the
start of winter, because bad weather meant an increase
in the number of customer trouble complaints. When
the complaints reached a certain volume, the application
came to a virtual standstill. The
business would then have to move to “manual”
operation. By meeting with the stakeholders I was
able to see a more complete picture, not just my manager’s
perspective on the project.
Has
your manager identified and assessed all major milestones,
cross-functional impacts and risks?
After identifying
the stakeholder expectations, I immediately set out
to determine how the manager arrived at a proposed
three-month completion date. Did
his project plan address the cross-functional risks?
Was it realistic and well thought through?
Your
challenge is to quickly ascertain whether the manager
has identified all tasks, impacts and risks across
multiple departments and outside vendors. Meet face
to face with your manager. Doing this
enables you to listen to the facts while also observing
the manager’s confidence in the project plan.
Having the
manager demonstrate how he came up with his time frame
for completion was the quickest, most tangible way
to assess whether his project plan was attainable.
Twenty minutes into our meeting I discovered
that key factors which would influence time frames
had not been verified. Certainly as a good manager
he knew what they were, but he and his team had guessed
on many timeframes. This meant that the team
had no idea how long this project would take to complete.
Substantially missing the expected completion date
on a project hurts professional credibility—both
the project sponsors’ and the responsible manager’s.
It became clear to
both the manager and me that a dedicated project manager
was needed. This person would have the singular time
and focus to flush out all of the activities and their
interdependencies.
Typically
the only business measure of a project’s success
is whether it met the original stakeholders expectations
within the constraints of the business case. In this
instance, I am happy to say it did. A
good project manager can not only fix problems like
the ones I’ve listed, but they can usually prevent
them before a single dollar is spent.